Notice of Study Commencement 
February 2023

Environmental Clearance 
Fall 2024

Notice of Completion
30-day public review of the TESR
Summer 2024

Preliminary Design of the TPA
Spring/Summer 2024

Public Information Centre #2
Present the Technically Preferred Alternative (TPA)
April 2024

Public Information Centre #1
Present the Short-Listed Alternatives
June 2023

We are here!

Comparative Evaluation
of the Short-Listed Alternatives
Winter 2024

Detail Design Phase
2024 - 2025